Level 1/2/3/4/5 Schedules

What are these "Level 1/2/3/4/5" schedules?

Schedule “levels” describe the amount of detail in a programme, similar to zoom levels on a map.
•  Level 1 (Master/Executive Summary):
A handful of key phases and milestones — suited to board packs and
executive reporting.

Level 2 (Summary Schedule):
Major work areas, disciplines, or facilities rolled up — used for client monthly
reporting.

Level 3 (Project/Control Schedule):
The most commonly used level — a fully logic-linked programme broken
down by area, discipline, or WBS, used to actually run the job on a weekly/monthly cycle. This is the schedule most contracts across mining, oil & gas, utilities, and commercial construction require as the contractual baseline.

Level 4 (Detailed Work Schedule):
A weekly cut for supervisors and leading hands, resource-loaded to control
day-to-day productivity.

Level 5 (Daily Plan)
The most granular level — daily task lists for crews, or hour-by-hour for high-intensity
work like a shutdown or turnaround.
Level 1/2/3/4/5 Schedules

Why it matters

Using the wrong level for the wrong audience causes real problems: a Level 5 daily task list is unusable in a board report, and a Level 1 milestone chart is useless for actually running a crew day to day. Most contractors need a solid Level 3 to satisfy contractual requirements and a Level 4 to run the job on-site — everything else can usually be generated from that same underlying schedule rather than maintained separately.

What's included in our deliverable

When to order one

Level 1-2 for executive and client reporting; Level 3 as your contractual baseline; Level 4 for site supervision; Level 5 only where daily or hourly-level control is genuinely required (common on shutdowns, turnarounds, and highly constrained work fronts).